Relocating an Electricity Meter — Steps, Cost, and How Long It Takes
You extended the house and the meter is in the way, you want it moved to another pole, or it blocks construction — all of that is 'relocating the meter', a job the utility must survey on site and charge for. This page lays out where to apply, what documents to prepare, roughly how long it takes, and how it differs from a name transfer or a new meter.
Relocating an electricity meter means moving the same existing meter to a new position/pole, for the same user and the same premises. Apply at MEA via MEASY or an MEA district office, or at PEA via the PEA Smart Plus app or a PEA office. The fee is assessed on site by distance and the materials required — there is no flat, publicly published rate — and the timeline runs after the on-site survey and payment. Full details below. (Changing the name or requesting a brand-new meter are different things — see the comparison section.)
How much does it cost to relocate an electricity meter?
How long does relocation take, and what documents do you need?
The electricity user's ID card (the name registered on the meter) — PEA accepts the ThaID app; non-Thais use a passport.
The customer account number (CA) and a recent bill, to identify the meter to be moved.
Proof of ownership/right to the land/building (title deed/contract), or the owner's written consent if the applicant is a tenant/not the owner.
A sketch/photo of the desired new position (if any) helps staff assess faster — confirm the actual document list on 1130/1129 before you go.
How is relocation different from a name transfer or a new meter?
| Request | What it does | When to use |
|---|---|---|
| Relocate (this page) | Move the same meter to a new position/pole; same user & premises | Extension, moving to another pole, meter blocking construction |
| Name transfer | Change the registered user name on the same meter; same location | Buying/selling a home, inheritance, moving in, new tenant |
| New meter | Request a new connection where there is no meter yet | New house, new building, a new point of use |
| Cancel meter | Remove the meter + reclaim the electricity deposit | Demolition, stopping electricity use at that point for good |
Which situations actually need a meter relocation?
Relocating a meter — the 4 steps
The same sequence at MEA and PEA — only the online channel differs. The key: wait for the assessment before paying, and never agree a price with anyone outside the utility.
File the relocation request
MEA: file via MEASY or an MEA district office · PEA: file via the PEA Smart Plus app or your local PEA office, with the documents listed above.
Wait for the on-site survey + get the quote
Staff visit to check the old and new positions, the distance and the materials needed, then state the cost and timeframe. This step is where the price comes from — do not estimate it from word-of-mouth figures.
Pay per the assessment
Pay via the channel the utility specifies and keep the receipt as proof; the work timeframe starts counting after payment and scheduling.
Schedule the move + acceptance
The utility carries out the move on the appointed day; afterwards, check the meter works normally and the connections are sound. If you upsized at the same time, confirm the new size matches what you requested.
Relocate ≠ name transfer ≠ new meter — pick right before you go
Who wrote this page
Compiled by the CapSolar team, a commercial solar provider in Thailand, and reviewed by Frank Lee (Founder). The steps and channels cite MEA and PEA services whose accessibility we verified as of Aug 2026. The utilities do not publish a flat fee or timeline for meter relocation, so we say plainly that it is assessed on site and give the number to call — nothing here is invented.
FAQ
Keep reading
Apply for a New Meter — Cost & Steps
A new point with no power yet — fees by meter size.
Transfer the Electricity User Name
Buying/moving in — change the name on the same meter.
Cancel a Meter + Deposit Refund
Stopping for good — remove the meter, reclaim the deposit.
Electrical Fire Prevention
Electrical work must be to standard — causes, prevention, response.
Setting up power/solar for your business — right from the start?
For buildings and factories, CapSolar designs and installs solar to standard, cutting the bill long-term — free assessment, no obligation.